Termination is often seen as an automatic right where wrongful termination is remedied through contractual damages. The Superior Court of Massachusetts, in Vineyard Wind 1, LLC v GE Renewables US LLC,[1] looked at a situation which required divergence from such orthodox thinking, and instead issued a preliminary injunction restraining termination. The Court’s thinking has tangible ramifications for construction projects (including Offshore Wind) where Contractors and Sub-Contractors are in a “unique position” with “unique knowledge and expertise” and where “the project is at a critical phase” such that termination “would set the project back immeasurably and threaten… financing”.
Context
Vineyard Wind 1 (VW) is the developer of the USD 4.5 billion Offshore Wind Farm off the coast of Martha’s Vineyard in Massachusetts. GE Renewables (GE) designed, manufactured, installed, and agreed to maintain the project’s wind turbine generators (WTGs), which were built to GE’s proprietary specifications and operate on GE’s technology. GE entered into a Turbine Supply Agreement and a Service and Maintenance Agreement with VW. The project was two years behind schedule, in part due to GE-attributable defects in the “massive blades that [GE] was responsible for manufacturing and installing on the WTGs”.[2] The Engineer determined that GE was liable for claims worth over USD 0.5 billion. GE did not challenge the Engineer’s ‘Clause 3.5’ determination. VW began offsetting amounts commensurate with the Engineer’s determination against GE’s interim payments. GE issued a Termination Notice of the Turbine Supply Agreement, pursuant to VW’s failure to pay amounts due to GE exceeding 5% of the contract price. VW resisted the termination, filing an application for a preliminary injunction, which was upheld. It is understood that matter has recently settled.[3] The Court’s thinking may raise concerns with an array of contractors as to when a termination notice can be injuncted such that the contractor must continue to perform.
The Superior Court of Massachusetts’ Thinking
The Superior Court of Massachusetts granted a preliminary injunction restraining the Termination Notice and compelling GE to “not cease or alter performance of its works”.[4] This decision was upheld by the same Court in a Motion for Reconsideration after the project had reached Commercial Operation. The principles for granting a preliminary injunction in Massachusetts (as in many common law jurisdictions) were not in dispute: it must be likely that the plaintiff will succeed on the merits, the plaintiff will suffer irreparable harm absent injunctive relief, and this harm outweighs the potential harm to the defendant if injunctive relief is granted. The Court found that VW had a “reasonable likelihood of success” that there was no “amount due” given the Engineer’s determination and VW’s right to set-off. As with most FIDIC-based contracts, the contract made provision for challenging the Engineer’s determination, which GE had not followed. The amount set off exceeded 5% of the Contract Price in May 2025 (several months before the Termination Notice was issued in February 2026). The Court further noted that GE could have challenged the Engineer’s determination, but had not done so.[5]
The reasons for granting injunctive relief were:[6]
- The project was “at a critical phase” given that VW was in the process of triggering “Commercial Operation Date” for the purposes of its “Power Purchase Agreements”.
- GE was in a “unique position” with “unique knowledge and expertise”. The work required to bring the project to commercial viability was “highly dependent on [GE]’s capabilities, personnel and technology”.
- It was “fanciful” and “pretend” to suggest that VW could hire another contractor “to finish the installation and troubleshoot and modify [GE]’s proprietary design without [GE]’s specialized knowledge”.
The Court found that “[GE] would not be irreparably harmed by an injunction” since “barring [GE] from ceasing performance based on the Termination Notice would do nothing but hold [GE] to its contractual obligations.”[7]
In refusing to compel the issue of preliminary injunctive relief to arbitration, the Court suggested that it certainly had the power to decide matters of preliminary injunctive relief under the Contract. In doing so, the Court relied on Clause 20.8.1 allowing the “Parties to seek… urgent injunctive or declaratory relief through any competent court”. This was further supported by Clause 20.9.1, which required that “performance of the Works under the Contract shall continue during any dispute resolution process”.[8] Such provisions resemble clauses found in FIDIC dispute mechanisms,[9] and associated arbitral rules.[10] Interestingly, the Court also suggested in dicta that it may even have the power to resolve injunctive relief against termination “on more than a preliminary basis”, under the wording of Clause 20.8.1, although this issue did not develop further.
Our Thoughts
The Superior Court of Massachusetts decision may be surprising to some contractors given that it compels GE into specific performance. The outer parameters of the preliminary injunction were not tested as the matter was resolved amicably. By way of comparison, English courts have long held that final mandatory injunctions – amounting to specific performance – should not be awarded where they would require a party to “carry on an activity” of uncertain scope.[11] An English case has never arisen, on similar facts to the present, for an interim mandatory injunction under Section 44 of the Arbitration Act 1996.
Vineyard Wind is governed by Massachusetts law, but the Court’s thinking has tangible ramifications for contractors more generally, and especially those operating in Offshore Wind. We say this because Offshore Wind has a small number of specialist participants each holding “unique knowledge”. As the Court noted, the specialised nature of Offshore Wind construction means finding alternative contractors is unlikely. Given the preponderance of unique knowledge and expertise, such mandatory injunctions (even when amounting to specific performance) may now increase. Whether other jurisdictions now follow the reasoning applied in Massachusetts when deciding contractor’s right(s) to terminate will be of serious relevance to contract drafters and to contractors operating in specialised sectors similar to Offshore Wind.
[1] Vineyard Wind 1 LLC v GE Renewables US LLC, 2026 Mass. Super. Civil No. 26-1041-BLS1 [Memorandum and Order on Motion for Preliminary Injunction]; Vineyard Wind 1 LLC v GE Renewables US LLC 2026 Mass. Super. Lexis 36 [Memorandum and Order on Motions for Reconsideration of Injunction and to Stay Proceedings Pending Arbitration].
[2] 2026 Mass. Super. Civil No. 26-1041-BLS1, at p. 1.
[3] See, announcement at Vineyard Wind and GE Vernova Announce Resolution of Commercial Litigation | GE Vernova News.
[4] 2026 Mass. Super. Civil No. 26-1041-BLS1 (n. 1), at p. 5.
[5] 2026 Mass. Super. Civil No. 26-1041-BLS1 (n. 1), at p. 4.
[6] 2026 Mass. Super. Civil No. 26-1041-BLS1 (n .1), at pp. 4-5; 2026 Mass. Super. Lexis 36 (n. 1), at pp. 1-2.
[7] 2026 Mass. Super. Civil No. 26-1041-BLS1 (n. 1), at p. 5.
[8] 2026 Mass. Super. Lexis 36 (n. 1), at pp. 3-4.
[9] See FIDIC 2017, Clause 21.4.2 [Obtaining DAAB’s Decision]: “Unless the Contract has already been abandoned or terminated, the Parties shall continue to perform their obligations in accordance with the Contract”; Clause 21.6 [Arbitration]: “The obligations of the Parties… shall not be altered by reason of any arbitration being conducted during the progress of the Works”.
[10] See, for example, Article 29.2 ICC Arbitration Rules 2026.
[11] Co-operative Insurance v Argyll Stores Ltd. (H.L.(E.)) [1998] 1 A.C. 1, at p. 13.